The Reims Hospital Centre decided to build a 600 space multi-storey carpark on land it owned, previously occupied by a laundry, a waste management operation and a secondary heating structure which had been transferred to the Logistical facility.
The design-completion procedure was selected by the entity to build the structure. The M&G GROUP provided technical support to the project management from the implementation of the Detailed Technical Plan until the delivery of the carpark.
The design-completion procedure was selected by the entity to build the structure. The M&G GROUP provided technical support to the project management from the implementation of the Detailed Technical Plan until the delivery of the carpark.
Key figures
Surface area: 15,000 m² floor area
Number of spaces: 600 spaces
Total project cost: €6.5m
Project schedule: 2006-2009
Number of spaces: 600 spaces
Total project cost: €6.5m
Project schedule: 2006-2009
Client: Reims University Hospital Centre
Project Management Support: M&G GROUP
Conglomerate: PERTUY CONSTRUCTION (project mandatee) + VICTOR CASTRO (Architects)
Project Management Support: M&G GROUP
Conglomerate: PERTUY CONSTRUCTION (project mandatee) + VICTOR CASTRO (Architects)